ODOT Construction Alert on I-105

Work starts on I-105 Aug. 1

From ODOT:

We start paving nightly next week, the impacts and estimated schedule are outlined below for the upcoming lane and ramp closures. You can avoid delays by planning ahead and taking a different route.

To help get the work done faster and lessen the amount of time there will be traffic impacts, we are planning to have two weekends where we shift traffic, creating a dedicated work zone.

The first weekend shift we’ll move eastbound traffic into one of the westbound lanes. The second weekend we’ll move the westbound traffic into one of the eastbound lanes.

We have diagrams showing the plan for each of the weekend lane closures on our project webpage. 

Schedule

  • ​Aug. 1 – 3: We’ll start paving the road from Delta Highway to about Country Club Road. Expect single lane closures nightly, 8 p.m. to 5 a.m.
  • Aug. 4 – 7: Starting at 8 p.m., we will shift traffic to the westbound lanes near Country Club Road to past Coburg Road while we pave and apply permanent striping on the eastbound lanes. We will reopen lanes by 5 a.m. Monday. 
    Ramp closures during this time:
    • Country Club Road eastbound off-ramp from eastbound I-105.  
    • Coburg Road eastbound on-ramp to eastbound I-105.  
  • Aug. 8 – 10: We will pave eastbound lanes nightly, from 8 p.m. to 5 a.m. towards Springfield.
  • Aug. 11 – 14: Starting at 8 p.m., we will shift traffic to the eastbound lanes from Country Club Road to past Coburg Road while we pave and apply permanent striping on the westbound lanes. We will reopen lanes by 5 a.m. Monday. 
    Ramp closures during this time:
    • Country Club Road westbound on-ramp to westbound I-105.  
    • Coburg Road off-ramp from westbound I-105.  
  • Starting Aug. 15, we will apply new driving surfaces to the bridges and finish paving the on and off-ramps. You can expect single lane closures nightly, Sunday night through Friday morning, 8 p.m. to 5 a.m.
  • Next, we will install rumble strips and permanent striping.

Visit TripCheck.com for the most up to date information on traffic impacts.
Work is weather dependent and our schedule may change. 

Road Work AheadProject DetailsAs part of the project, we will:Repave I-105 and some I-105 and I-5 on and off-ramps.Remove and replace seven bridge deck surfaces.Add rumble strips between milepost 2.25 and 4.Add reflective strips to guardrails for improved visibility.

Discover more from Santa Clara Community Organization - Eugene

Subscribe to get the latest posts sent to your email.

This entry was posted in Transportation. Bookmark the permalink.

2 Responses to ODOT Construction Alert on I-105

  1. Tiffany Brant says:

    I cant find an appropriate place to report I-105 west pot hole. City maintenance said, call ODOT. When I called, it only said for urgent road hazards.

    Deep, sizeable , rectangular pot hole, west bound, just before Florence exit to west 6th ave.

    • Gary Haliski says:

      Sorry for the late response. This is the number I found (the Springfield office)
      2080 Laura Street
      Springfield, Oregon 97477 5
      41-744-8080
      And, yes, ODOT makes it difficult.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.