Santa Clara Transit Station Update August 3

You can get updates like the following from LTD by joining the email list on this web page – Santa Clara Transit Station. Look for the green tab near the top right if you visit the LTD page.

August 3 LTD update:

Current Status: Construction

LTD restroom construction for Santa Clara Transit Station

During the month of July, significant progress was made at the transit station and park and ride. At the driver relief building, the concrete slab was poured, the framing was completed and the electrical and plumbing rough-in began. As we enter August, electrical, plumbing and mechanical work will continue in the building and structural steel will be installed.

At the platform area, the concrete footings for the shelters were poured and electrical conduit for lighting was installed. The new shelters are currently being fabricated and are planned to be installed at the end of August.

The concrete curbs at the park and ride have been installed and work on storm water planters and general grading continues. Concrete curbs and sidewalks will continue to be poured throughout the station in August.

LTD Santa Clara Transit Station contsruction overhead picture.

Privately Engineered Public Improvements (PEPI) continued thru July. Conduit for the new traffic signal at the intersection of River Road and Green Lane was bored underground in July. The traffic signal pole foundations will be installed over the month of August while the actual traffic signal poles and arms are planned to be installed in September. In early August along Green Lane, EWEB will be installing electrical infrastructure underground and removing several poles. Following EWEB’s infrastructure install, construction efforts will begin along Green Lane and are expected to last two months. Green Lane will be stripped of the current asphalt and a new base will be constructed for the road. New asphalt will be laid and a sidewalk will be installed along the north side of Green Lane. During construction hours, Green Lane will be open to one-lane traffic. Flaggers will be on site to direct traffic around the construction. Outside of construction hours, Green Lane will be open for two-way traffic. The curbs for the new Elementary Lane were poured during July. In August, the sidewalk along the western side of Elementary Lane will be poured.

Traffic Impacts:
Green Lane will be open to one-lane traffic from River Road to the east end of the Santa Clara Transit Station during construction hours of 7:30 a.m. to 4:30 p.m. Flaggers will be directing traffic around the road construction; drivers, pedestrians, and bicyclists are encouraged to use caution when traveling on Green Lane. Outside of construction hours, Green Lane will be open for two-way traffic.


PROJECT OVERVIEW

In 2015, LTD purchased an 8-acre undeveloped parcel along River Road between Hunsaker Lane and Green Lane to pursue the design and construction of the Santa Clara Transit Station. This site was selected because the property allows for flexible development of a transit station and Park & Ride. The site provides sufficient space to allow for maximum maneuverability of buses and for better access for riders, pedestrians, cyclists, and people who use mobility devices. The design includes 6 bus bays, 55 parking spaces at the adjacent Park & Ride, on-street parking, secure bike parking, covered station platforms, and a small driver relief building.


For More Information: Randi Staudinger, LTD Project Manager, Randi.Staudinger@LTD.org
For Public Comment: SCTransit@LTD.org or 541-682-3240

Posted in LTD Transit Station, Transportation | Leave a comment

SCCO August Meeting – Thursday, Aug 6 7 PM ZOOM

The August 6th SCCO meeting will be held via ZOOM at 7PM. You can click on the image below this Thursday evening at 7PM to attend the meeting.

Posted in General Interest, Santa Clara Timber Projects, SCCO Meetings | Leave a comment

Beaver-Hunsaker improvement and Speed Reduction

From Lane County:

On July 28, 2020, the Lane County Board of Commissioners issued a temporary order (effective August 1, 2020 through August 1, 2022) to reduce the posted speeds to 25 mph on Hunsaker Lane and 30 mph on Beaver Street. Lane County staff will update the signage in the coming weeks. This change is intended to improve safety, in combination with physical changes to the roadway. Later this month (August 2020) the corridor will be repaved and restriped to create a wider shoulder on the south side of Hunsaker Lane. 

More improvements are planned for the spring of 2021, such as the installation of vertical delineators installed between the wider shoulder and vehicle travel lane, a pedestrian-crossing flashing beacon and construction of a multi-use path along the Delta Sand and Gravel frontage. The delineators will restrict parking on the shoulder in some areas. In the coming months, staff will be reaching out to affected property owners. 

We will continue to update you as more details become available. Please contact Becky Taylor, Senior Transportation Planner, at becky.taylor@lanecountyor.gov or 541-255-5761 if you have any questions.

SCCO recap:

  • Reduced speeds through August 1, 2022
  • Updated signage
  • Repaving & restriping
  • Pedestrian-crossing flashing beacon
  • Multi-use path along the Delta and and Gravel frontage!!!
Posted in Beaver-Hunsaker & Multi Use Path, General Interest | Tagged , , | Leave a comment

Saturday (July 24, 2020), casual meeting to discuss possible Awbrey Park timber projects, 11:30 at the Park.

If anyone is interested in discussing a possible project utilizing our urban-logged timber at Awbrey Park, I will be hanging out at the park from 11:30 to 12:30, Saturday July 24, 2020 with a lawn chair and a distancing stick. Please bring a chair or blanket, carry a mask, come with an open mind and maybe a picnic lunch! See you then.

See the urban-logging and sawmill operations slideshow here: https://www.youtube.com/watch?v=pfSUtY-fmZU&feature=youtu.be

Posted in Santa Clara Timber Projects | Leave a comment

Urban Reserves Options Survey Closes This Sunday July 26th

The Urban Reserves Technical Group reached out at the beginning of July for feedback regarding reserving land outside the UGB for future UGB expansion. Please take the survey linked below. SCCO recommends both the 10-year and 27-year options as they exclude the most valuable close-in agricultural lands from consideration for any UGB expansion.

In case you missed it, they want to let you know that the Urban Reserves Options Survey is open for only 2 more days–the last day to take the survey is this Sunday July 26th. Please tell them what you think about the four Urban Reserves options under consideration, and spread the word with your networks. Folks that take the survey by Sunday July 26th will have the chance to win a $100 grocery gift card. They will be presenting survey results to the Eugene Planning Commission on August 3rd and to the Lane County Planning Commission on August 4th and want to make sure we hear from you before thenThank you!

Posted in General Interest, Land Use Planning, Parks and Natural Resources | Leave a comment